Multiple Choice
The forward pass in project network calculations determines all of the following EXCEPT
A) Earliest time an activity can begin.
B) Earliest time an activity can finish.
C) Duration of the project.
D) The critical path.
E) How soon the project can finish.
Correct Answer:

Verified
Correct Answer:
Verified