The WBS Is Best Suited for Projects That Have a Tangible

Question 88

Multiple Choice

The WBS is best suited for projects that have a tangible outcome. Which of the following is used when the final outcome of the project is less tangible or is a product of a series of steps or phases?


A) Responsibility matrix
B) Organization breakdown structure
C) A work breakdown structure is still effective for these types of projects.
D) Priority matrix
E) Process breakdown structure

Correct Answer: