Multiple Choice
Which of the following best describes the overall goal of project portfolio management?
A) Maximize support of business strategy while minimizing risk.
B) Maximize innovation at an affordable cost.
C) Ensure that all projects are selected using the same criteria.
D) Select projects that can easily be terminated if not successful.
Correct Answer:

Verified
Correct Answer: