Multiple Choice
The theory of constraints says that
A) queues should not be allowed to form in the plant.
B) bottleneck resources should be idle whenever possible.
C) the bottleneck is the most critical resource.
D) labor expense reduction should be the primary goal.
Correct Answer:

Verified
Correct Answer:
Verified