Multiple Choice
Which of the following is a tactic for reducing demand pressure on a process bottleneck?
A) Place a quality inspection point immediately before the bottleneck.
B) Decrease the size of batches run through the bottleneck (assuming setup required) .
C) Increase inventory levels at the non-bottleneck resources.
D) All of the above.