Multiple Choice
A node has one entering activity, a, and two leaving activities, b and c. Given the following information, determine the latest starting time for activity a: EFb = 15, EFc = 17, LFb = 24, LFc = 27; activity times are a = 4, b = 6, c = 8.
A) 14
B) 15
C) 16
D) 17
E) 18
Correct Answer:

Verified
Correct Answer:
Verified
Q55: Consider the following work breakdown structure:<br><img src="https://d2lvgg3v3hfg70.cloudfront.net/TB8594/.jpg"
Q56: Which decision in project management has typical
Q57: A hierarchical listing of what must be
Q58: A Gantt chart is apopular visual tool
Q59: In "crashing" a project, a manager will
Q61: Consider the following work breakdown structure:<br><img src="https://d2lvgg3v3hfg70.cloudfront.net/TB8594/.jpg"
Q62: Consider the following work breakdown structure:<br><img src="https://d2lvgg3v3hfg70.cloudfront.net/TB8594/.jpg"
Q63: Shortening activity durations is called<br>A)expediting.<br>B)crashing.<br>C)vendor management.<br>D)null nodes.<br>E)trade-off
Q64: Which decision in project management has typical
Q65: There are four activities on the critical