Consider the Following Work Breakdown Structure What Is the Estimated Slack Time for Activity W?
A)
Multiple Choice
Consider the following work breakdown structure: What is the estimated slack time for activity W?
A) 0 days
B) 25 days
C) 35 days
D) 45 days
E) 85 days
Correct Answer:

Verified
Correct Answer:
Verified