Solved

Consider the Following Work Breakdown Structure What Is the Estimated Expected (Mean) Time for Project Completion

Question 28

Multiple Choice

Consider the following work breakdown structure:  Time Estimates (days)   Activity  Precedes  Optimistic  Most Likely  Pessimistic  Start  A, B  A  C, D 445056 B  D 456075 C  E 424548 D  F 314049 E  F 273639 F  End 587082\begin{array}{l}\begin{array} { l c c c c } &&&\text { Time Estimates (days) }\\\text { Activity } & \text { Precedes } & \text { Optimistic } & \text { Most Likely } & \text { Pessimistic } \\\hline \text { Start } & \text { A, B } & - & - & - \\\text { A } & \text { C, D } & 44 & 50 & 56 \\\text { B } & \text { D } & 45 & 60 & 75 \\\text { C } & \text { E } & 42 & 45 & 48 \\\text { D } & \text { F } & 31 & 40 & 49 \\\text { E } & \text { F } & 27 & 36 & 39 \\\text { F } & \text { End } & 58 & 70 & 82\end{array}\end{array} What is the estimated expected (mean) time for project completion?


A) 160 days
B) 170 days
C) 200 days
D) 210 days
E) 300 days

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions