A project consists of nine major activities, as shown below. There are three separate paths in the network: a-c-f, b-d-g, and e-h-i.
(A) What is expected project duration time?
(B) Determine the probability that the project will take more than 35 weeks to complete. (All times are in weeks.)
Correct Answer:

Verified
(A) Expected duration = 32 wee...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q27: Activity J has a duration of 7
Q38: In a project network, the critical path
Q76: Project management differs from management of more
Q83: Some organizations use a matrix organization to
Q87: Which of the following is not an
Q94: Deterministic networks use three time estimates-shortest, most
Q96: The main function of dummy activities is
Q116: Once a project is underway, the project
Q130: Consider the following work breakdown structure:
Q133: Consider the following work breakdown structure: