Multiple Choice
In an assignment method problem, if it takes Abe 3 hours to build a birdhouse and 4 hours for a doghouse, while Betty takes 4 hours for a birdhouse and 3 hours for a doghouse, what is the reduced cost (in hours) of assigning Abe to build the doghouse?
A) 0 hours
B) 1 hour
C) 2 hours
D) 3 hours
E) 4 hours
Correct Answer:

Verified
Correct Answer:
Verified