The Owner/operator of the Local Franchise of Handyman, Inc If He Uses the Shortest Processing Time First Priority Rule
Multiple Choice
The owner/operator of the local franchise of Handyman, Inc., has four jobs to do today, shown in the order they were received: If he uses the shortest processing time first priority rule to schedule these jobs, what will be the average number of jobs in his shop today?
A) 0
B) 1
C) 2
D) 3
E) 4