Short Answer
Given the following data for jobs awaiting processing at a manufacturing cell in which jobs are first processed by machine A, then by machine B:
In developing the sequence which will minimize throughput time, what is the initial job to be placed in the schedule sequence?
Correct Answer:

Verified
Correct Answer:
Verified