True/False
In a CPM analysis if you subtract the early finish from the late finish the result is the activity's slack time.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q15: A series of projects that are organized
Q19: Which of the following is a graphic
Q24: A project can be subdivided into which
Q26: You have just performed a Single Time
Q29: To calculate the variances of activity times
Q31: The "Z" value used to calculate the
Q32: Project Management can be defined as planning,directing
Q33: Describe how CPM handles the trade-offs between
Q33: Below are the data for a
Q90: The critical path of activities in a