Solved

Below Are the Data for a Time-Cost CPM Scheduling Model

Question 33

Multiple Choice

Below are the data for a Time-Cost CPM Scheduling model analysis.The time is in days and the costs include both direct and indirect costs.  Immediate  Normal  Crash  Normal  Crash  Activity  Predecessor  Time  Time  Cost  Cost  A  None 32$200$400 B  A 43$300$600 C  A 11$200$200 D  B and C 32$500$550 E  D 21$500$900\begin{array}{|l|l|l|l|l|l|}\hline & \text { Immediate } & \text { Normal } & \text { Crash } & \text { Normal } & \text { Crash } \\\hline \text { Activity } & \text { Predecessor } & \text { Time } & \text { Time } & \text { Cost } & \text { Cost } \\\hline \text { A } & \text { None } & 3 & 2 & \$ 200 & \$ 400 \\\hline \text { B } & \text { A } & 4 & 3 & \$ 300 & \$ 600 \\\hline \text { C } & \text { A } & 1 & 1 & \$ 200 & \$ 200 \\\hline \text { D } & \text { B and C } & 3 & 2 & \$ 500 & \$ 550 \\\hline \text { E } & \text { D } & 2 & 1 & \$ 500 & \$ 900 \\\hline\end{array}
What are the total time of this project and total normal cost?


A) Total time is 13 days,total cost is $1,200
B) Total time is 12 days,total cost is $1,700
C) Total time is 11 days,total cost is $1,600
D) Total time is 10 days,total cost is $1,750
E) Total time is 9 days,total cost is $1,700

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions