    To Calculate the Variances of Activity Times in CPM Analysis
Solved

To Calculate the Variances of Activity Times in CPM Analysis

Question 29

Question 29

True/False

To calculate the variances of activity times in CPM analysis we must use all three time estimates (i.e. ,optimistic,most likely and pessimistic time estimates).

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q15: A series of projects that are organized

Q24: A project can be subdivided into which

Q26: You have just performed a Single Time

Q28: In a CPM analysis if you subtract

Q31: The "Z" value used to calculate the

Q32: Project Management can be defined as planning,directing

Q33: Describe how CPM handles the trade-offs between

Q33: Below are the data for a

Q34: The second step in managing a project

Q90: The critical path of activities in a

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines