A simple project listing of five activities,their predecessors and their respective time estimates are presented below:  Activity  Immediate Predecessor  Time in Days  A  None 2 B  A 2 C  A 1 D  B and C 3 E  D 1\begin{array}{|l|l|l|}\hline \text { Activity } & \text { Immediate Predecessor } & \text { Time in Days } \\\hline \text { A } & \text { None } & 2 \\\hline \text { B } & \text { A } & 2 \\\hline \text { C } & \text { A } & 1 \\\hline \text { D } & \text { B and C } & 3 \\\hline \text { E } & \text { D } & 1 \\\hline\end{array}
Using the Single Time Estimate CPM procedure,which activities have slack in this project?


A) A
B) B
C) C
D) D
E) C and E