Multiple Choice
Below are the data for a Time-Cost CPM Scheduling analysis.The time is in days and the costs include both direct and indirect costs.
If you crash this project to reduce the total time by four days,what is the total time of the project and total cost?
A) Total time is 10 days,total cost is $2,500
B) Total time is 9 days,total cost is $2,300
C) Total time is 8 days,total cost is $2,750
D) Total time is 8 days,total cost is $1,850
E) Total time is 9 days,total cost is $2,350
Correct Answer:

Verified
Correct Answer:
Verified
Q18: Some of the advantages of a functional
Q39: Calculating the early start and early finish
Q43: In a Gantt chart, the horizontal axis
Q82: A simple project listing of five
Q83: If the pessimistic duration of an activity
Q84: One of the assumptions of CPM is
Q85: We assume in CPM analysis that the
Q88: A company must perform a maintenance
Q90: You ask your subordinates how long it
Q104: In CPM, the late start time estimate