Below Are the Data for a Time-Cost CPM Scheduling Analysis

Question 86

Multiple Choice

Below are the data for a Time-Cost CPM Scheduling analysis.The time is in days and the costs include both direct and indirect costs.  Immediate  Normal  Crash  Normal  Crash  Activity  Predecessor  Time  Time  Cost  Cost  A  None 32$200$400 B  A 43$300$600 C  A 11$300$300 D  B and C 32$500$550 E  D 21$500$900\begin{array}{|l|l|l|l|l|l|}\hline & \text { Immediate } & \text { Normal } & \text { Crash } & \text { Normal } & \text { Crash } \\\hline \text { Activity } & \text { Predecessor } & \text { Time } & \text { Time } & \text { Cost } & \text { Cost } \\\hline \text { A } & \text { None } & 3 & 2 & \$ 200 & \$ 400 \\\hline \text { B } & \text { A } & 4 & 3 & \$ 300 & \$ 600 \\\hline \text { C } & \text { A } & 1 & 1 & \$ 300 & \$ 300 \\\hline \text { D } & \text { B and C } & 3 & 2 & \$ 500 & \$ 550 \\\hline \text { E } & \text { D } & 2 & 1 & \$ 500 & \$ 900 \\\hline\end{array}
If you crash this project to reduce the total time by four days,what is the total time of the project and total cost?


A) Total time is 10 days,total cost is $2,500
B) Total time is 9 days,total cost is $2,300
C) Total time is 8 days,total cost is $2,750
D) Total time is 8 days,total cost is $1,850
E) Total time is 9 days,total cost is $2,350