A Company Must Perform a Maintenance Project Consisting of Seven

Question 40

Multiple Choice

A company must perform a maintenance project consisting of seven activities.The activities,their predecessors and their respective time estimates are presented below:  Immediate  Activity  Designation  Predecessor  Time in Days  Break down both machines  A  None 3 Clean machine 1  B  A 3 Clean machine 2  C  A 3 Re-set machine 1  D  B 4 Re-set machine 2  E  C 2 Re-calibrate both machines  F  D and E 1 Final test  G  F 2\begin{array}{|l|l|l|l|}\hline & & \text { Immediate } & \\\hline \text { Activity } & \text { Designation } & \text { Predecessor } & \text { Time in Days } \\\hline \text { Break down both machines } & \text { A } & \text { None } & 3 \\\hline \text { Clean machine 1 } & \text { B } & \text { A } & 3 \\\hline \text { Clean machine 2 } & \text { C } & \text { A } & 3 \\\hline \text { Re-set machine 1 } & \text { D } & \text { B } & 4 \\\hline \text { Re-set machine 2 } & \text { E } & \text { C } & 2 \\\hline \text { Re-calibrate both machines } & \text { F } & \text { D and E } & 1 \\\hline \text { Final test } & \text { G } & \text { F } & 2 \\\hline\end{array}
Using the Single Time Estimate CPM procedure,which activities make up the critical path?


A) A,B,D,F,G
B) A,C,E,F,G
C) A,C,B,F,E
D) A,D,E
E) None of the above

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions