Multiple Choice
Below are the data for a Time-Cost CPM Scheduling model analysis.The time is in days and the costs include both direct and indirect costs.
If you crash this project to reduce the total time by one day what is the total time of the project and total cost?
A) Total time is 13 days,total cost is $1,500
B) Total time is 12 days,total cost is $2,000
C) Total time is 12 days,total cost is $2,300
D) Total time is 11 days,total cost is $1,850
E) Total time is 11 days,total cost is $2,350
Correct Answer:

Verified
Correct Answer:
Verified
Q29: The Gantt chart is an example of
Q32: Project Management can be defined as planning,directing
Q32: Project management software available today combines CPM
Q33: Below are the data for a
Q34: The second step in managing a project
Q36: The work breakdown structure (WBS)defines a hierarchy
Q38: A company wants to use CPM analysis
Q40: A company must perform a maintenance
Q42: Which of the following is a reason
Q70: A disadvantage of a matrix project organizational