Which of the following is an assumption made in using CPM analysis?
A) Project activities flow together without distinct boundaries
B) Project activity times can be estimated accurately and do not vary
C) Project management should focus on crashing activities
D) There is never a work stoppage in any activity until it is complete
E) There are no learning curve effects in setting activity time
Correct Answer:

Verified
Correct Answer:
Verified