Multiple Choice
A company must perform a maintenance project consisting of seven activities.The activities,their predecessors and their respective time estimates are presented below:
Using the Single Time Estimate CPM procedure,which activities have slack in this project?
A) A,B,C
B) B,D
C) Only C
D) C,E
E) F,G
Correct Answer:

Verified
Correct Answer:
Verified