Multiple Choice
You ask your subordinates how long it will take to complete the job they are working on.The subordinates say,"If everything goes right it will take 6 hours,most likely it will take 8 hours and if everything goes wrong it will take until the end of tomorrow or another 16 hours".Since this job is a part of a larger project you must estimate the expected time it will take to complete the job.Using the three activity time estimation procedure for CPM,what is the expected time for this job?
A) 8 hours
B) 9 hours
C) 10 hours
D) 11 hours
E) 12 hours
Correct Answer:

Verified
Correct Answer:
Verified
Q18: Some of the advantages of a functional
Q39: Calculating the early start and early finish
Q43: In a Gantt chart, the horizontal axis
Q47: One of the disadvantages of a pure
Q72: The critical path in a CPM analysis
Q85: We assume in CPM analysis that the
Q86: Below are the data for a
Q88: A company must perform a maintenance
Q92: A matrix project structure may be referred
Q95: If you have an optimistic time of