Multiple Choice
If the pessimistic duration of an activity is 24,the most likely duration is 15 and the optimistic duration is 6,what is the variance for the activity time when using CPM analysis?
A) 6
B) 8.333
C) 9
D) 10.4
E) 12
Correct Answer:

Verified
Correct Answer:
Verified