Question 49

Multiple Choice

You have the following time and cost information below for use in a Time-Cost CPM Scheduling model.  Activity  Normal Time  Crash Time  Normal Cost  Crash Cost  A 32$400$600 B 53$600$1200 C 41$300$1500\begin{array}{|l|l|l|l|l|}\hline \text { Activity } & \text { Normal Time } & \text { Crash Time } & \text { Normal Cost } & \text { Crash Cost } \\\hline \text { A } & 3 & 2 & \$ 400 & \$ 600 \\\hline \text { B } & 5 & 3 & \$ 600 & \$ 1200 \\\hline \text { C } & 4 & 1 & \$ 300 & \$ 1500 \\\hline\end{array}
What are the three costs per unit of time to expedite each activity?


A) A=$300,B=$200,C=$300
B) A=$100,B=$200,C=$400
C) A=$200,B=$200,C=$200
D) A=$100,B=$400,C=$300
E) A=$200,B=$300,C=$400

Correct Answer: