Multiple Choice
Critical Ratio is:
A) The ratio of processing time to idle time of the process
B) The ratio of remaining time until due date to the remaining processing time
C) Greater than one if the job is behind schedule
D) All of the above
Correct Answer:

Verified
Correct Answer:
Verified