All of the following are characteristics of the postcompletion phase of a project except ____.
A) confirm that the final project meets the expectations of management or customers
B) reassign project personnel to other positions or other projects
C) restore any equipment and facilities used to their original status
D) conduct a postimplementation meeting to discuss the strengths and weaknesses of the project
E) identify broad budget, personnel, and resource requirements