Multiple Choice
If a project path has an expected duration of 10 days and a standard deviation of 3 days, what is the probability that the path will be completed in 13 days or less?
A) 50 percent
B) 33 percent
C) 75 percent
D) 84 percent
Correct Answer:

Verified
Correct Answer:
Verified