A Project Is Composed of 6 Activities That Have Durations

Question 56

Multiple Choice

A project is composed of 6 activities that have durations and precedence requirements shown in the table. Which of these activities is NOT on the critical path?  Activity  Length  Predecessor  A 5 B 7 A  C 4 A  D 7 B,C  E 7 B  F 6 D, E \begin{array} { | c | c | c | } \hline \text { Activity } & \text { Length } & \text { Predecessor } \\\hline \text { A } & 5 & \cdots \\\hline \text { B } & 7 & \text { A } \\\hline \text { C } & 4 & \text { A } \\\hline \text { D } & 7 & \text { B,C } \\\hline \text { E } & 7 & \text { B } \\\hline \text { F } & 6 & \text { D, E } \\\hline\end{array}


A) A
B) B
C) C
D) D