    What Is the Latest That Activity D Can Start If
Solved

What Is the Latest That Activity D Can Start If

Question 55

Question 55

Multiple Choice

What is the latest that activity D can start if A lasts 5 days, B lasts 7 days, C lasts 4 days, D lasts 5 days, E lasts 7 days, and F is 6 days long? What is the latest that activity D can start if A lasts 5 days, B lasts 7 days, C lasts 4 days, D lasts 5 days, E lasts 7 days, and F is 6 days long?   A) 14 B) 15 C) 16 D) 17


A) 14
B) 15
C) 16
D) 17

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q50: Performance or time targets for each major

Q51: The university president concocts a thirteen-step

Q52: Which of these needs does the Guide

Q53: A hatmaker, fresh off a very

Q54: Construction of the cattery could be

Q56: A project is composed of 6

Q57: The tablet unearthed by the archaeologist

Q58: In what way are projects and typical

Q59: Given the earliest and latest finish

Q60: A Gantt chart provides both a planning

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines