Multiple Choice
A company currently has no items in inventory. The demand for the next four months is 200, 400, 250, and 350 units. Assuming a level production rate of 250 units per month, determine the months in which backorders or stockouts will materialize.
A) Only in month 1
B) In months 2 and 4
C) In months 2, 3, and 4
D) In months 2 and 3
Correct Answer:

Verified
Correct Answer:
Verified