Multiple Choice
Capacity requirements are computed by multiplying the number of units scheduled for production at a work center by:
A) the setup time and then subtracting the unit resource requirements.
B) the setup time and then adding the unit resource requirements.
C) the unit resource requirements and then adding in the setup time.
D) the unit resource requirements and then subtracting the setup time.
Correct Answer:

Verified
Correct Answer:
Verified
Q8: What is capacity requirements planning (CRP)?
Q9: Explain the three levels of resource planning.
Q10: Which lot sizing rule is best when
Q11: Resources include materials, equipment, facilities, information, technical
Q12: A company currently has no items in
Q14: The bill of material (BOM) for
Q15: If A has a gross requirement to
Q16: Level 3 planning, i.e. detailed planning and
Q17: Which is the most comprehensive solution for
Q18: Define a master production schedule (MPS) and