Consider the Following Project Network -In the Previous Project Network, the Critical Path Activities Are

Question 33

Multiple Choice

Consider the following project network. Time estimates are in weeks.  Consider the following project network. Time estimates are in weeks.   Complete the following table and questions :  \begin{array} { | c | l | l | l | l | l | l | l | }  \hline \text { Activity } & \text { Time } & \text { Earliest Start } & \text { Earliest Finish } & \text { Latest Start } & \text { Latest Finish } & \text { Slack } & \text { On Critical Path? } \\ \hline \text { A } & & & & & & & \\ \hline \text { B } & & & & & & & \\ \hline \text { C } & & & & & & & \\ \hline \text { D } & & & & & & & \\ \hline \text { E } & & & & & & & \\ \hline \text { F } & & & & & & \\ \hline \end{array}   \begin{array}{|c|c|c|c|c|c|c|c|} \hline \text { Activity } & \text { Duration } & \text { ES } & \text { EF } & \text { LS } & \text { LF } & \text { Slack } & \begin{array}{c} \text { On } \\ \text { CP? } \end{array} \\ \hline \text { A } & 2 & 0 & 2 & 0 & 2 & 0 & \text { yes } \\ \hline \text { B } & 4 & 2 & 6 & 2 & 6 & 0 & \text { yes } \\ \hline \text { C } & 5 & 6 & 11 & 6 & 11 & 0 & \text { yes } \\ \hline \text { D } & 4 & 11 & 15 & 11 & 15 & 0 & \text { yes } \\ \hline \text { E } & 6 & 2 & 8 & 9 & 15 & 7 & \text { no } \\ \hline \text { F } & 7 & 15 & 22 & 15 & 22 & 0 & \text { yes } \\ \hline \end{array}  -In the previous project network, the critical path activities are: A)  A,B, and C. B)  A,B,C,D, and F. C)  A,B,D, and F. D)  B,C,D, and F. Complete the following table and questions :  Activity  Time  Earliest Start  Earliest Finish  Latest Start  Latest Finish  Slack  On Critical Path?  A  B  C  D  E  F \begin{array} { | c | l | l | l | l | l | l | l | } \hline \text { Activity } & \text { Time } & \text { Earliest Start } & \text { Earliest Finish } & \text { Latest Start } & \text { Latest Finish } & \text { Slack } & \text { On Critical Path? } \\\hline \text { A } & & & & & & & \\\hline \text { B } & & & & & & & \\\hline \text { C } & & & & & & & \\\hline \text { D } & & & & & & & \\\hline \text { E } & & & & & & & \\\hline \text { F } & & & & & & \\\hline\end{array}  Activity  Duration  ES  EF  LS  LF  Slack  On  CP?  A 202020 yes  B 426260 yes  C 56116110 yes  D 4111511150 yes  E 6289157 no  F 7152215220 yes \begin{array}{|c|c|c|c|c|c|c|c|}\hline \text { Activity } & \text { Duration } & \text { ES } & \text { EF } & \text { LS } & \text { LF } & \text { Slack } & \begin{array}{c}\text { On } \\\text { CP? }\end{array} \\\hline \text { A } & 2 & 0 & 2 & 0 & 2 & 0 & \text { yes } \\\hline \text { B } & 4 & 2 & 6 & 2 & 6 & 0 & \text { yes } \\\hline \text { C } & 5 & 6 & 11 & 6 & 11 & 0 & \text { yes } \\\hline \text { D } & 4 & 11 & 15 & 11 & 15 & 0 & \text { yes } \\\hline \text { E } & 6 & 2 & 8 & 9 & 15 & 7 & \text { no } \\\hline \text { F } & 7 & 15 & 22 & 15 & 22 & 0 & \text { yes } \\\hline\end{array}
-In the previous project network, the critical path activities are:


A) A,B, and C.
B) A,B,C,D, and F.
C) A,B,D, and F.
D) B,C,D, and F.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions