The slack for an activity is equal to its latest finish time minus its earliest start time.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q24: Project managers need to be specialists, not

Q25: Based on Alternative Water Supply-Single Project case

Q26: _ is the sequence of activities that

Q27: Slack in an activity is computed as:<br>A)

Q28: Describe the four major steps in the

Q30: The county government has decided to redo

Q31: In which stage of the project life

Q32: A high definition television manufacturer in

Q33: Consider the following project network. Time

Q34: When finding the earliest start (ES) time

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines