You Are Responsible for Managing an Advertising Project with the Following
Question 36
Question 36
Multiple Choice
You are responsible for managing an advertising project with the following activities (times are given in weeks) . Activity A B C D E F G Immediate Predecessor none none none A, B C A D. E F Normal Time (Weeks) 3625274 Crash Time (Weeks) 2613163 Normal Cost ($) $14,000$5,500$6,000$7,500$9,000$15,000$8,400 Crash Cost ($) $16,500$5,500$8,000$14,500$10,500$18,000$10,000 Draw the project network here. BLANK SPACES -What is the critical path for this project?
A) A-D-G B) A-F-G C) B-D-G D) C-E-G
Correct Answer: