_____ Is the Sequence of Activities That Takes the Longest

Question 26

Multiple Choice

_____ is the sequence of activities that takes the longest time and defines the total project completion time.


A) Project Evaluation and Review Technique
B) The critical path
C) The crash time
D) Project nodes network