    A Consistent Time Base, Such as Hours or Days or Weeks
Solved

A Consistent Time Base, Such as Hours or Days or Weeks

Question 61

Question 61

True/False

A consistent time base, such as hours or days or weeks, should be used for all the estimated durations of activities in a network diagram.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q56: The sponsor or customer often states the

Q57: An updated project schedule can be generated

Q58: The estimated duration should be aggressive and

Q59: Changes requested early in the project always

Q60: Positive slack indicates the maximum amount of

Q62: Each organization or subcontractor responsible for a

Q63: The estimated types and quantities of resources

Q64: The _ and _ times are determined

Q65: The _ and _ times are determined

Q66: Calculate the latest start for Task D

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines