Question 103

Multiple Choice

The estimated duration for each activity is indicated by a bar spanning the period


A) during which the activity is expected to be accomplished.
B) of the part of the activity that has more than one work resource assigned.
C) during which the activity has waiting time for the activity to be accomplished.
D) during which the project is expected to be accomplished.