Multiple Choice
The estimated duration for each activity is indicated by a bar spanning the period
A) during which the activity is expected to be accomplished.
B) of the part of the activity that has more than one work resource assigned.
C) during which the activity has waiting time for the activity to be accomplished.
D) during which the project is expected to be accomplished.
Correct Answer:

Verified
Correct Answer:
Verified
Q98: It is necessary to monitor the progress
Q99: Calculate the latest finish for Task B
Q100: Earliest start time (ES)is the earliest time
Q101: This longest path in the overall network
Q102: The amount of slack should determine the
Q104: For large projects that involve several hundred
Q105: Total slack for the project is the
Q106: Calculate the earliest start for Task B
Q107: Earliest finish time (EF)is the earliest time
Q108: The total completion time is 25 days.Task