An assembly line with 28 operations is to be balanced.The total amount of time required for all 28 operations is 39 minutes.The longest operation takes 2.2 minutes and the shortest takes 0.8 minutes.The line will operate for 450 minutes per day.
1. Determine the minimum and maximum cycle time.
2. What is the output rate if the cycle time is set at 2.2 minutes?
A) min cycle time = 0.8; max cycle time = 39; output rate = 204.5
B) min cycle time = 2.2; max cycle time = 39; output rate = 204.5
C) min cycle time = 2.2; max cycle time = 31.2; output rate = 562.5
D) min cycle time = 0.8; max cycle time = 2.2; output rate = 562.5
Correct Answer:

Verified
Correct Answer:
Verified
Q5: Explain the role of ergonomics in job
Q20: For the following assembly line data, balance
Q21: The determination of specific job tasks and
Q22: An assembly line with 28 activities is
Q23: _ set their own goals and inspect
Q26: All of the following are common objectives
Q27: Discuss the advantages and disadvantages of utilizing
Q28: A company is setting up an assembly
Q30: The Florida Appliance Company is installing an
Q74: An assembly line is a type of