Multiple Choice
Assembly line balancing
A) Is a one-time activity.
B) Tries to minimize the production rate for a given number of work stations.
C) Tries to minimize the number of work stations for a given production rate.
D) Attempts to load work into early work stations.
Correct Answer:

Verified
Correct Answer:
Verified