Essay
A small electronics company assembles power supplies for use in computers, printers and Fax machines.They want to set up an assembly line to make their operation more efficient and plan to use line balancing with the longest-task-time heuristic.The demand for power supplies is 70 per hour, and the productive time per hour is 52 minutes.The following table provides details on their operation.
a.What is the cycle time?
b.What is the theoretical minimum number of workstations?
c.What tasks go into the first workstation?
d.How many workstations are needed for the entire line?
e.What is the assembly-line efficiency?
Correct Answer:

Verified
a.Cycle time = 54 min per hr./80 units p...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q48: Workers in cellular layouts generally have greater
Q66: Virtual teams are empowered work teams that
Q70: Which is true for product layout?<br>A)Very flexible<br>B)Lower
Q71: An assembly line with 28 activities is
Q72: The nine tasks necessary to assemble a
Q73: Because of precedence relationships, assembly-line efficiencies will
Q74: List the many questions that must be
Q77: Assembly line balancing<br>A)Is a one-time activity.<br>B)Tries to
Q78: Assembly-line balancing problems involving many distinct products
Q78: Which of the following is not a