Essay
The following five jobs, along with their processing time and due dates, are given below.
a.Use the Shortest Processing Time Rule (SPT) and determine the average flow-time for the five jobs
b.Use the Earliest Due Date Rule (EDD) and determine the average lateness and tardiness.