Multiple Choice
A project has three paths.A-B-C has a length of 25 days.A-D-C has a length of 15 days.Finally, A-E-C has a length of 20 days.Which one of the following statements is true?
A) A-D-C is the critical path.
B) A-B-C has the most slack.
C) The expected duration of this project is 25 days.
D) The expected duration of this project is 25 + 15 + 20 = 60 days.