Data regarding the activities for a project are presented below.The times are in weeks.The critical path for this project is A - D - H - I - J - K.
a.Determine the standard deviation of the critical path.
b.Determine the probability of completing the project in 38 weeks or less.
c.What is the probability of completing the project in 32 weeks or less?
Correct Answer:

Verified
a.Variance calculations are shown below....View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q27: Slack in an activity is computed as:<br>A)
Q30: Activity times must be estimated from historical
Q32: When finding the earliest finish (EF) time
Q34: A project has three paths.A-B-C has a
Q37: A type of organization which "loans" resources
Q39: Which of the following is not an
Q40: In a matrix organization, functional managers may
Q42: Define a project. Give some non-manufacturing or
Q80: Explain the purpose of Gantt charts.
Q93: When the beta probability distribution is used