Multiple Choice
Which of the following is not an assumption of the critical path method?
A) Activities are independent of one another
B) Activity time estimates are stable
C) Activity times are characterized by a beta probability distribution
D) Once an activity is started it continues uninterrupted until completion
Correct Answer:

Verified
Correct Answer: