Multiple Choice
-Network logic suggests that:
A) Activity D can start any time.
B) Activity A must be complete before Activity B can be done.
C) Activities A, B and C must be complete before Activity D can be done.
D) Activity C must begin before Activity B begins.
Correct Answer:

Verified
Correct Answer:
Verified
Q8: An activity has an optimistic time estimate
Q19: An activity has a pessimistic time that
Q21: Activities C,D,and E in the project represented
Q26: Burst activities are those with two or
Q29: What is the background of CPM and
Q34: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6815/.jpg" alt=" -Use the network
Q36: What is the early start time
Q40: A gentleman farmer maniacally works on
Q44: The variance of an activity is given
Q80: Preceding activities are those that must occur