Multiple Choice
A gentleman farmer maniacally works on academic projects to raise funds for his true passion,farming.He has identified seven tasks and developed three time estimates (all in days) of the next big project on the farm,replacing the fence at the comedy pasture.Tasks,precedence requirements,and time estimates are shown in the table.What is the expected completion time of the project?
A) 32 days
B) 33 days
C) 34 days
D) 35 days
Correct Answer:

Verified
Correct Answer:
Verified
Q8: An activity has an optimistic time estimate
Q19: An activity has a pessimistic time that
Q21: Activities C,D,and E in the project represented
Q26: Burst activities are those with two or
Q34: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6815/.jpg" alt=" -Use the network
Q36: What is the early start time
Q39: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5361/.jpg" alt=" -Network logic suggests
Q44: The variance of an activity is given
Q75: Serial activities are those that:<br>A)Flow from one
Q80: Preceding activities are those that must occur