What is the slack time for Activity B given the activity times and precedence requirements shown in the table?  Activity  Time  Predecessor  A 5 B 7 C 8 A  D 7 A  E 4 B  G 8 C, D  H 9 E, F \begin{array} { | l | l | l | } \hline \text { Activity } & \text { Time } & \text { Predecessor } \\\hline \text { A } & 5 & - - \\\hline \text { B } & 7 & - - \\\hline \text { C } & 8 & \text { A } \\\hline \text { D } & 7 & \text { A } \\\hline \text { E } & 4 & \text { B } \\\hline \text { G } & 8 & \text { C, D } \\\hline \text { H } & 9 & \text { E, F } \\\hline\end{array}


A) 10
B) 9
C) 8
D) 7