Multiple Choice
Project Test Bank is composed of activities we will refer to as A,B,C,and D for convenience (and lack of creativity) .Durations and precedence requirements are shown in the table.Each of these activities can be conveniently laddered into two sub-activities of equal duration,so activity C in the original project becomes two activities,C1 and C2,each of which lasts 7 days.The first half of each activity serves as the predecessor to its second half and the first half of the original following activity.What is the difference in the late start time for activity C in the original project and activity C1 in the laddered project?
A) 3
B) 5
C) 7
D) 9
Correct Answer:

Verified
Correct Answer:
Verified
Q48: Activity float is the difference between the
Q49: An activity has an optimistic time estimate
Q78: What is the slack time for
Q80: A gentleman farmer maniacally works on
Q81: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5361/.jpg" alt=" -Activities C,D,and E
Q84: Use the values in the table
Q85: What is the slack time for
Q88: Activities C,D,and E in the project represented
Q100: What is the underlying theory to the
Q103: These can be located by doing a