What is the slack time for activity E?  Early  Early  Late  Late \cline57 Task  Predecessor  Duration  Start  Finish  Start  Finish A8BA14CA238DC,B62326EC32FD,E3238\begin{array} { | l | l | l | l | l | l | l | } \hline & & & \text { Early } & \text { Early } & \text { Late } & \text { Late } \\\cline { 5 - 7 } \text { Task } & \text { Predecessor } & \text { Duration } & \text { Start } & \text { Finish } & \text { Start } & \text { Finish } \\\hline \mathrm { A } & - & 8 & & & & \\\hline \mathrm { B } & \mathrm { A } & & & & 14 & \\\hline \mathrm { C } & \mathrm { A } & & & 23 & 8 & \\\hline \mathrm { D } & \mathrm { C } , \mathrm { B } & 6 & 23 & & 26 & \\\hline \mathbb { E } & \mathrm { C } & & & 32 & & \\\hline \mathbb { F } & \mathrm { D } , \mathrm { E } & & 32 & & & 38 \\\hline\end{array}


A) 0 days
B) 1 day
C) 2 days
D) 4 days

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions