    Exam 9: Project Scheduling: Networks, Duration Estimation, and Critical Path
  5. Question
    A Project's Duration Can Be Reduced By
Solved

A Project's Duration Can Be Reduced By

Question 60

Question 60

Multiple Choice

A project's duration can be reduced by:


A) Shortening the duration of critical path tasks.
B) Adding tasks to the critical path.
C) Adding shorter routes around the critical path.
D) Completing the backward pass first.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q55: An activity has an optimistic time estimate

Q56: One of the defining points of a

Q57: There's an old saying,"The job is not

Q58: Phoebe B.Beebee is constructing a canal

Q59: A gentleman farmer maniacally works on

Q61: Use the values in the table

Q62: The length of time expected to complete

Q63: An activity has an optimistic time estimate

Q64: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB6815/.jpg" alt=" -Use the network

Q65: A backward pass is performed when it

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines